Deliverable 1

Draft Assignment Inception Report

Component 1: Legislative reform

Deliverable 2

Final Inception Report

Deliverable 3

Draft Final Country Diagnostic and Reform Agenda

Deliverable 4

Final Country Diagnostic and Reform Agenda

Deliverable 5:

Preliminary Drafts on New Decrees on procurement planning, exterritorial government entities, framework agreements

Component 1: Legislative reform

Deliverable 6

Final Drafts on New Decrees on procurement planning, exterritorial government entities, framework agreements

Deliverable 7

Draft Report on review and revision of existing draft decrees (eProcurement, pre-qualification, eProcurement user manuals) to be submitted to the OL as defined in the Final Assignment Inception Report)

Deliverable 8

Final Report on review and revision of existing draft decrees (eProcurement, pre-qualification, eProcurement user manuals) to be submitted to the OL as defined in the Final Assignment Inception Report)

Deliverable 9

Draft of standard tender documents for framework agreements and call offs under framework agreement, suitable for eProcurement to be submitted to the OL as defined in the Final Assignment Inception Report

Deliverable 10

Final standard tender documents for framework agreements and call offs under framework agreement, suitable for eProcurement to be submitted to the OL, no later than 5 working days after having received the OL’s comments on the draft report

Deliverable 11

Draft of standard tender documents and template contracts for goods and services, suitable for eProcurement to be submitted to the OL as defined in the Final Assignment Inception Report

Deliverable 12

Final standard tender documents and template contracts for goods and services, suitable for eProcurement to be submitted to the OL, no later than 5 working days after having received the OL’s comments on the draft report

Deliverable 13

Draft Agenda and draft training materials for “Procurement monitoring – procedures and training session” – to be submitted to the OL as defined in the Final Assignment Inception Report

Component 4: Regulatory Capacity Building

Deliverable 14

Final Agenda and draft training materials for “Procurement monitoring – procedures and training session” to be submitted to the OL, no later than 5 working days after having received the OL’s comments on the draft report

Deliverable  15

Training session “Procurement monitoring and procedures”

Deliverable  16

Draft Agenda and draft training materials for “Public Procurement regulatory training (Sustainability)” to be submitted to the OL as defined in the Final Assignment Inception Report

Deliverable  17

Final Agenda and draft training materials for “Public Procurement regulatory training (Sustainability)” to be submitted to the OL, no later than 5 working days after having received the OL’s comments on the draft report

Deliverable  18

Public Procurement regulatory training (Sustainability)

Deliverable  19

Draft Agenda and draft training materials for “Public procurement capacity building/training session based on the localised SIGMA training toolkit (Procurement Support Centre) to be submitted to the OL as defined in the Final Assignment Inception Report

Deliverable  20

Final Agenda and final training materials for “Public procurement capacity building/training session based on the localised SIGMA training toolkit (Procurement Support Centre) to be submitted to the OL, no later than 5 working days after having received the OL’s comments on the draft report

Deliverable  21

Public procurement capacity building/training session based on the localised SIGMA training toolkit (Procurement Support Centre)

Deliverable 22

Draft Final Report

Component 1: Legislative reform

Component 4: Regulatory capacity building

Deliverable 23

Final Report to be submitted to the OL, no later than 10 working days after having received the OL’s comments on the draft version

 

 

 

Project Deliverables: Phase 2

 

Deliverable 1

Draft Memorandum on Armenian eProcurement system with comments on response from European Dynamics of January 18, 2013 to the diagnostic report evaluating the ARMEPS (eProcurement system in Armenia) prepared by the consultant in October 2012

Component 2: eProcurement reform

Deliverable 2

Final Memorandum on Armenian eProcurement system to be submitted to the OL no later than 5 working days after having received the OL’s comments on the draft report

Deliverable 3

Draft Revised Road Map including comments and proposal from the World Bank and other EBRD UNCITRAL Initiative partners in Armenia

Deliverable 4

Final Revised Road Map and Work Plan to be submitted to the OL no later than 7 working days after completion of the mission. The Final Work Plan 2013 will include a precise and confirmed with the Government of Armenia and international donors Work Plan including specific targets and milestones for working on public procurement reform in 2013. Final Road Map and Work Plan will be provided in English and Armenian.

Deliverable 5:

Draft Comments and Revisions of the Final Draft of the eProcurement Decree to be submitted to the OL if requested, in English

Component 1: Legislative reform

Deliverable 6

Final Comments and Revisions of the Final Draft of the eProcurement Decree, in English and Armenian

Deliverable 7

Finalise Procurement Planning decree, in English and Armenian

Deliverable 8

Finalise Framework agreement decree, in English and Armenian

Deliverable 9

Develop Procurement Monitoring decree, in English and Armenian

Deliverable 10

Analyse key implementation documents produced by selected provider. Take into account the road map/work plan as appropriate and recirculate to RA

Component 2: eProcurement reform

Deliverable 11

New procurement planning module - originally outside scope of ARMEPS. Establish RA functional requirements by reference to procurement planning decree and consultation with RA stakeholders. Review technical solutions against RA requirements. Establish if Procurement planning best done within or outside ARMEPS. Review the Armenian government budget planning system (LS Budget) to make sure that information related to the procurement plan can be imported from there (or any other third party information system).

Deliverable 12

Purchase of e-catalogues module. Review possible technical solutions against RA requirements and document final business requirements, aligning with procurement decree, procurement planning decree and framework agreement decree. Prepare statement of requirements document in preparation for procurement of the e-catalogues module.

Deliverable 13

e-reverse auctions. Establish strategy for using existing e-reverse auction module (including for framework agreements)

Deliverable 14

ARMEPS upgrade TOR and RFP

 

Deliverable 15

Capacity building activities.     Phase 1 - Legislation adopted in 2013. Phase 2 - Procurement skills: regulatory, procuring entities, suppliers, including SMEs. Phase 3 - Legislation adopted in 2014

Component 4: Regulatory capacity building

     

       Project Deliverables 2014: Phase 3

Deliverable 1

Review of the detailed Project Implementation Plan produced by PSC/EKENG. The review has to be completed in 3 days after the receipt of the final PIP from PSC/EKENG.

Component 2: eProcurement reform

Deliverable 2

Update of the Road Map for Finalising eProcurement Reform in Republic of Armenia 2013-2015 prepared by the team in December 2012 due to the change of stakeholders and role allocations. Necessary amendments have to be made also in the Armenian version of the text. The final English text of the Road Map has to be submitted to the OL by the end of January 2014.

Deliverable 3

Update of the Work Plan based on the updated Road Map to be submitted to the OL together with the Road Map in the end of January 2014.

Deliverable 4

Draft report on the revision of ARMEPS eProcurement system functionality after the update including comments and proposals from the Armenian stakeholders (MoF, PSC, EKENG). The report has to provide information on whether after the update the system is able to work without discrepancies and if this is not the case contain list of bugs necessary to eliminate. It has to be based on the review of the test plan prepared by PSC/EKENG.

Deliverable 5

Final report on the revision of ARMEPS eProcurement system functionality after the update to be submitted to OL in English.

Deliverable 6

Update of the ARMEPS eProcurement system Users Manuals to be submitted to the PSC in Armenian and to OL in English if requested. Updated User Manuals have to include all new features of the system regarding FA.

Deliverable 7

Draft Technical Specifications for the web-site for Procurement Support Centre, in English and Armenian.

Deliverable 8

Final Technical Specifications for the web-site for Procurement Support Centre, in English and Armenian.

Deliverable 9

Report on the functionality of planning e-tool developed by LSOFT. The report must contain information on whether the produced tool can be used as an ARMEPS procurement planning module, whether the databases can be transferred and systems can be interoperable.

Deliverable 10

New procurement planning, reporting and contract management modules - originally outside scope of ARMEPS. Establish RA functional requirements by reference to procurement planning and reporting decrees and consultation with RA stakeholders.  Specifications and functionality update considering new GFMIS system implementation project activities.

Component 2: eProcurement reform

Deliverable 11

Purchase of new procurement planning, reporting and contract management modules - originally outside scope of ARMEPS.

Deliverable 12

Purchase of web-site development services for the Procurement Support Centre.

 

Deliverable 13

Final Framework Agreement decree that includes all the comments from 60 central government bodies in English and Armenian.

Component 1: Legislative reform

Deliverable 14

Final Procurement Reporting decree that includes all the comments from 60 central government bodies in English and Armenian.

Deliverable 15

Final Procurement Planning decree that includes all the comments from 60 central government bodies in English and Armenian.

Deliverable 16

Final eProcurement Decree that includes all the comments from 60 central government bodies in English and Armenian.

Deliverable 17

Legislative drafting: amendment of the existing primary and secondary legislation to comply with the new WTO GPA rules.

Component 1: Legislative reform

Component 3: Harmonisation with revised WTO GPA 2012

Deliverable 18

Legislative drafting: amendment of the existing primary and secondary legislation to comply with the Customs Union rules.

Component 1: Legislative reform

Deliverable 19

Capacity building activities.    

Phase 2 - Procurement skills: regulatory, procuring entities, suppliers, including SMEs. Phase 3 - Legislation adopted in 2014

Component 4: Regulatory Capacity Building

 


Allocation of deliverables to experts and their progress:

Deliverable

Short Description

Experts

Progress in the reporting period

Next period

Deliverable 1

Draft Memorandum on Armenian eProcurement system with comments on response from European Dynamics of January 18, 2013 to the diagnostic report evaluating the ARMEPS (eProcurement system in Armenia) prepared by the consultant in October 2012.

Chris Smith

Astghik Solomonyan

Finalised

 

Deliverable 2

Final Memorandum on Armenian eProcurement system to be submitted to the OL no later than 5 working days after having received the OL’s comments on the draft report.

Chris Smith

Astghik Solomonyan

Finalised

 

Deliverable 3

Draft Revised Road Map including comments and proposal from the World Bank and other EBRD UNCITRAL Initiative partners in Armenia.

Chris Smith

Artak Chobanyan

Finalised

 

Deliverable 4

Final Revised Road Map and Work Plan to be submitted to the OL no later than 7 working days after completion of the mission. The Final Work Plan 2013 will include a precise and confirmed with the Government of Armenia and international donors Work Plan including specific targets and milestones for working on public procurement reform in 2013. Final Road Map and Work Plan will be provided in English and Armenian.

Chris Smith

Artak Chobanyan

The new Roadmap included the whole ePPS and related aspects, such as legislation framework development, capacity building activities, knowledge transfer, explanations and definitions.

Road Map was approved by the government stakeholders’ meeting at the Prime Minister’s office on 20 February 2013.

Regarding the ARMEPS system current issues and changed schedules, the Roadmap was outdated. See the revised Work Plan in annex.              

The Crown Agents consultants’ eProcurement team has to review the Roadmap and update as much as necessary based on new work plan. New revised version of roadmap will be issued during June 2014.

Deliverable 5:

Draft Comments and Revisions of the Final Draft of the eProcurement Decree to be submitted to the OL if requested, in English.

Chris Smith

Astghik Solomonyan

Artak Chobanyan

Draft decree (no final version of the decree)

Final comments and suggestions will be received from the Armenian stakeholders before official adoption

Deliverable 6

Final Comments and Revisions of the Final Draft of the eProcurement Decree, in English and Armenian

Chris Smith

Artak Chobanyan

The recent eProcurement decree April 2014, should be revised

 

Deliverable 7

Finalise Procurement Planning decree, in English and Armenian

Paulo Magina

Astghik Solomonyan

Finalised

 

Deliverable 8

Finalise Framework agreement decree, in English and Armenian

Paulo Magina

Astghik Solomonyan

Finalised

 

Deliverable 9

Develop Procurement Monitoring decree, in English and Armenian

Paulo Magina

Astghik Solomonyan

Artak Chobanyan

Draft version issued and sent to the Ministry of Finance for internal circulation

 

Deliverable 10

Analyse key implementation documents produced by selected provider. Take into account the road map/work plan as appropriate and recirculate to RA.

Paulo Magina

Chris Smith

Artak Chobanyan

Key implementation documents reviewed version will be issued with the new revised Roadmap

 

Deliverable 11

New procurement planning module - originally outside scope of ARMEPS. Establish RA functional requirements by reference to procurement planning decree and consultation with RA stakeholders. Review any other and RA technical solutions against RA requirements. Establish if Procurement planning best done within or outside ARMEPS

Paulo Magina

Artak Chobanyan

 

Tender in progress and the supplier selection in final negotiation stage

Minor changes will be needed in draft planning decree considering planning module final functionality

Deliverable 12

Purchase of e-catalogues module. Review any other technical solutions against RA requirements, and document final business requirements, aligning with procurement decree, procurement planning decree and framework agreement decree. Prepare statement of requirements document in preparation for procurement of the e-catalogues module.

Paulo Magina

Artak Chobanyan

 

Functional and technical requirements should be developed before the start of the new modules purchasing procedure

Deliverable 13

e-reverse auctions. Establish strategy for using existing e-reverse auction module (including for framework agreements)

Paulo Magina

 

 

Deliverable 14

ARMEPS upgrade TOR and RFP

Paulo Magina

Chris Smith

Artak Chobanyan

Draft version developed by the international and local team

Functional assessment of existing system to identify operational level and integration with implemented new modules (planning, contract management and reporting)

Deliverable 15

Capacity building activities.             

Phase 1 - Legislation adopted in 2013.

Phase 2 - Procurement skills: regulatory, procuring entities, suppliers, including SMEs.

Phase 3 - Legislation adopted in 2014

Paulo Magina

Astghik Solomonyan

Artak Chobanyan

Joint EBRD-TAIEX capacity building session with the Treasury of the Republic of Cyprus

13-15 June 2013,

capacity building session explaining new draft laws: framework agreements

2-3 July 2013, 2-4 Sept 2013, 14-16 Oct  2013,

joint EBRD-TAIEX capacity building session with the Portuguese Public Procurement Agency, 23-24 Sept 2013

 

 

Project Deliverables 2014: Phase 3

Deliverable

Short Description

Experts

Progress in the reporting period

Next period

Deliverable 1

Review of the detailed Project Implementation Plan produced by PSC/EKENG. The review has to be completed in 3 days after the receipt of the final PIP from PSC/EKENG.

Chris Smith

Artak Chobanyan

Drafted in the roadmap

Will be reissued after the new roadmap approval

Deliverable 2

Update of the Road Map for Finalising eProcurement Reform in Republic of Armenia 2013-2015 prepared by the team in December 2012 due to the change of stakeholders and role allocations. Necessary amendments have to be made also in the Armenian version of the text. The final English text of the Road Map has to be submitted to the OL by the end of January 2014.

Chris Smith

Artak Chobanyan

Astghik Solomonyan

 

Consultants team working for new version of roadmap with the major changes, taking into the consideration existing bugs in the ARMEPS functionality as well as future development options for new additional modules

Will be issued in new revised version

Deliverable 3

Update of the Work Plan based on the updated Road Map to be submitted to the OL together with the Road Map in the end of January 2014

Chris Smith

Artak Chobanyan

Astghik Solomonyan

 

Latest approved project plan almost outdate

Will be reissued after the new roadmap approval

Deliverable 4

Draft report on the revision of ARMEPS eProcurement system functionality after the update, including comments and proposals from the Armenian stakeholders (MoF, PSC, EKENG). The report must provide information on whether after the update the system is able to work without discrepancies and if not,  to list the bugs to be eliminated. It has to be based on the review of the test plan prepared by PSC/EKENG.

Chris Smith

Artak Chobanyan

Astghik Solomonyan

 

Shortcoming list and supported documents available

Functional assessment of existing system to identify operational level and integration with implemented new modules (planning, contract management and reporting)

Deliverable 5

Final report on the revision of ARMEPS eProcurement system functionality after the update to be submitted to OL in English.

Chris Smith

Artak Chobanyan

Astghik Solomonyan

Levon Hovsepyan

Paulo Magina

 

 

Deliverable 6

Update of the ARMEPS user manuals, to be submitted to the PSC in Armenian and to OL in English if requested. Updated user manuals must include all new features of the system regarding FAs.

Chris Smith

Artak Chobanyan

Paulo Magina

Draft version as well as interactive manuals drafts developed for current ARMEPS users (CA and EO)

Finalisation of drafts

Deliverable 7

Draft Technical Specifications for the website for Procurement Support Centre, in English and Armenian

Chris Smith

Artak Chobanyan

Finalised

 

Deliverable 8

Final Technical Specifications for the web-site for Procurement Support Centre, in English and Armenian

Chris Smith

Artak Chobanyan

This document was finalised in December 2013; the next step will be the tender announcement by PSC.

Tendering for web page development should be announced shortly.

Deliverable 9

Report on the functionality of planning e-tool developed by LSOFT. The report must contain information on whether the produced tool can be used as an ARMEPS procurement planning module, whether the databases can be transferred and systems can be interoperable.

Artak Chobanyan

Finalised

 

Deliverable 10

New procurement planning, reporting and contract management modules - originally outside scope of ARMEPS. Establish RA functional requirements by reference to procurement planning and reporting decrees and consultation with RA stakeholders.

Chris Smith

Artak Chobanyan

Tender announced in December 2014 and is on final evaluation for supplier selection now

Modules development, deployment and integration

Deliverable 11

Purchase of new procurement planning, reporting and contract management modules

Chris Smith

Artak Chobanyan

Supplier selection finalised and signed contract by the MoF for new modules development

New modules will be available by the end of current year.

Deliverable 12

Purchase of web-site development services for Ministry of Finance

Artak Chobanyan

New web portal for Single point of access to the all public procurement information

Technical and functional specifications should be drafted.

Deliverable 13

Final Framework Agreement decree that includes all the comments from 60 central government bodies in English and Armenian

Paulo Magina

Astghik Solomonyan

Olivier Moreau

The final version is drafted.

Minor update before official circulation

Deliverable 14

Final Procurement Reporting decree that includes all the comments from 60 central government bodies in English and Armenian.

Artak Chobanyan

The final version is drafted.

Sent MoF

Deliverable 15

Final Procurement Planning decree that includes all the comments from 60 central government bodies in English and Armenian.

Artak Chobanyan

Olivier Moreau

The final version is drafted.

Sent MoF

Deliverable 16

Final eProcurement Decree that includes all the comments from 60 central government bodies in English and Armenian.

Chris Smith

Artak Chobanyan

Olivier Moreau

The final version is drafted.

Minor revision will be nodded after new modules implementation.

Deliverable 17

Legislative drafting: amendment of the existing primary and secondary legislation to comply with the new WTO GPA rules.

Johannes Schnitzer

Astghik Solomonyan

A Concept Note describing the main directions of future amendments to the PPL was drafted and sent to international counterparts for review. The Concept Note was sent to the Government staff on 27th of Aptil 2015. It was redrafted and sent to the Government staff once again on 1 June 2015.

Drafting the amendments to the Armenian primary legislation in compliance with the new GPA text.

Deliverable 18

Legislative drafting: amendment of the existing primary and secondary legislation to comply with the Customs Union rules.

Johannes Schnitzer

Astghik Solomonyan

A Concept Note describing the main directions of future amendments to the PPL was drafted and sent to international counterparts for review. The Concept Note was sent to the Government staff on 27 April 2015. It was redrafted and sent to the Government staff once again on 1 June 2015.

Drafting the amendments to the Armenian primary legislation in compliance with Customs Union Agreement.

Deliverable 19

Capacity building activities.

Phase 2 - procurement skills: regulatory, procuring entities, suppliers, including SMEs.

Phase 3 - legislation adopted in 2014

Artak Chobanyan

Astghik Solomonyan

Capacity building activity to discuss GPA new text. Donors – EBRD jointly with WTO GPA Secretariat and US CLDP. Dates – 25-27 April 2014. Participants – staff of the Ministry of Finance, “Procurement Support Centre” SNCO, contracting authorities, NGOs, etc.

Capacity building activities for business environment in all regions of Armenia started from October 2014 and lasted until the end of November. The main aim is to provide primary information to the business people on how they can participate to public procurement, how to use ARMEPS, etc. In October-November 9 regions out of 10 were visited by Consultants. Syuniq regional seminar was postponed due to weather conditions.

Deliverable 20

Public procurement single point of access portal design and development support

Artak Chobanyan

Portal look and feel prepared and shared to the MoF for further discussion.

Functional and technical requirements draft

Deliverable 21

Public procurement new portal functionality extension, interactive user manuals and training tools development

Artak Chobanyan

New functionality basic topics discussed with the MoF  and preliminary agreed by them.

Functional and technical requirements draft

 

 

 

 
© 2011 European Bank for Reconstruction and Development | E-mail Us | Terms and Conditions | Users | godaddy